Transmission links Β· Ayrshire / North Wales

Western HVDC Link

Operating

The operating Western Link connects Hunterston to Flintshire Bridge. Its route is approximately 420 km, including 385 km subsea. It carries electricity between Scotland and Wales and is a separate asset from the proposed Western Link 2.

Sources reviewed 2026-10-08 Β· SP Energy Networks / National Grid

Project facts

StatusOperating
Developer / operatorSP Energy Networks / National Grid
RegionAyrshire / North Wales
CountryUnited Kingdom
Published rating2,200 MW
Rating definitionPublished transfer capacity
Connection / routeHunterston ↔ Flintshire Bridge / Connah’s Quay
Delivery targetNot verified in this profile
Total route length420 km
Subsea section385 km

What this link contributes

This asset provides a route for electricity to move between networks or strengthens the network carrying that electricity. Its capacity cannot be added to wind, solar or power-station capacity as though it were another generator.

Hunterston ↔ Flintshire Bridge / Connah’s Quay

Converter stations, cable manufacture, offshore installation, landfall works and grid energisation can progress at different times. The status above describes the documented project stage rather than assuming all work packages are complete.

Project location

Connection sites and areas are shown separately. Dashed circles mark approximate endpoint areas. No straight line is presented as the cable or overhead-line route.

Loading OpenStreetMap…

Markers identify sites, published points or labelled connection areas. Markers are not site boundaries or entrances. EGL2’s additional outlines and route layers are explicitly identified in the developer’s map data.

Sources and review date

  1. Operator route and operation
    Reviewed 2026-10-08
  2. Published 2,200 MW design
    Reviewed 2026-10-08

How Octary distinguishes proposals, published ratings and live measurements

Report a correction with a source

GRID CONTEXT