Transmission links · Orkney / Caithness

Orkney–Caithness Transmission Link

Under construction

Underground cable installation began in September 2026. The scheme includes Finstown substation, a 14 km land cable to Warebeth and a 53 km subsea cable to Dounreay. It creates Orkney’s first connection to the mainland transmission network.

Sources reviewed 2026-10-08 · SSEN Transmission

Project facts

StatusUnder construction
Developer / operatorSSEN Transmission
RegionOrkney / Caithness
CountryScotland
Published rating220 MW
Rating definitionTransfer capacity
Connection / routeFinstown ↔ Dounreay
Delivery targetNot verified in this profile
Voltage220 kV
Subsea section53 km

What this link contributes

This asset provides a route for electricity to move between networks or strengthens the network carrying that electricity. Its capacity cannot be added to wind, solar or power-station capacity as though it were another generator.

Finstown ↔ Dounreay

Converter stations, cable manufacture, offshore installation, landfall works and grid energisation can progress at different times. The status above describes the documented project stage rather than assuming all work packages are complete.

Project location

Connection sites and areas are shown separately. Dashed circles mark approximate endpoint areas. No straight line is presented as the cable or overhead-line route.

Loading OpenStreetMap…

Markers identify sites, published points or labelled connection areas. Markers are not site boundaries or entrances. EGL2’s additional outlines and route layers are explicitly identified in the developer’s map data.

Sources and review date

  1. SSEN Transmission project information
    Reviewed 2026-10-08

How Octary distinguishes proposals, published ratings and live measurements

Report a correction with a source

GRID CONTEXT

Great Britain electricity now

Explore the grid →
Loading the latest published grid interval…

National figures from the Carbon Intensity API. These do not measure an individual project’s output, cable flow or data-centre electricity use.